Project progress

previous arrow
next arrow
previous arrownext arrow
Slider

OVERALL CONSTRUCTION WORK : WORK COMPLETE 68.90%
– PILING WORK : 100%
– STRUCTURAL WORK : 87.21%
– ARCHITECTURAL WORK : 57.93%
– MECHANICAL WORK : 42.90%

PREVIEW DETAIL
– STRUCTURE WORK : WE COMPLETE ON 34MTH FLOOR. NOW POOL STRUCTURE 35TH FL. ON PROCESS OF CONSTRUCTION.
– ARCHITECT WORK : WORKING PROCESS ON 1ST TO 30TH FLOOR.
– MECHANICAL & ELECTRICAL : WORKING PROCESS ON 1ST TO 29TH FLOOR.
– ROAD & HARDSCAPE : NOW RC-STRUCTURE (BEAM&SLAB) FINISH 30% OF PROJECT AREA.