Project progress

previous arrow
next arrow
previous arrownext arrow
Slider

OVERALL CONSTRUCTION WORK : WORK COMPLETE 53.52%
– PILING WORK : 100%
– STRUCTURAL WORK : 79.48%
– ARCHITECTURAL WORK : 25.32%
– MECHANICAL WORK : 19.45%

PREVIEW DETAIL
– STRUCTURE WORK : COMPLETE ON 30TH FLOOR
– ARCHITECT WORK : WORKING PROCESS ON 1ST TO 25TH FLOOR
– MECHANICAL & ELECTRICAL : WORKING PROCESS ON 1ST TO 24TH FLOOR
– ROAD 8 HARDSCAPE : START PILING WORK & RC-STRUCTURE WORK