Project progress

previous arrow
next arrow
previous arrownext arrow
Slider

OVERALL CONSTRUCTION WORK : WORK COMPLETE 84.95.%
– PILING WORK : 100%
– STRUCTURAL WORK : 93.75%
– ARCHITECTURAL WORK : 69.32%
– MECHANICAL WORK : 67.43%