Project progress

previous arrow
next arrow
previous arrownext arrow
Slider

OVER ALL CONSTRUCTION : WORK COMPLETE 48.73%
– PILING WORK : 100%
– STRUCTURE WORK : 52.35%
– ARCHITECTURE WORK : 14.23%
– M&W WORK : 12.65%

PREVIEW DETAIL :
– STRUCTURE WORK : POURING SLAB COMPLETE ON 25TH FLOOR.
– ARCHITECT WORK : WORKING PROCESS ON 8TH TO 19TH FLOOR.
– MECHANICAL & ELECTRICAL : WORKING PROCESS ON 8TH TO 19TH FLOOR