Project progress

previous arrow
next arrow
previous arrownext arrow
Slider

OVERALL CONSTRUCTION WORK : WORK COMPLETE 55.41%
– PILING WORK : 100%
– STRUCTURAL WORK : 84.21%
– ARCHITECTURAL WORK : 38.84%
– MECHANICAL WORK : 35.90%

PREVIEW DETAIL
– STRUCTURE WORK : WE COMPLETE ON 32ND FLOOR.
– ARCHITECT WORK : WORKING PROCESS ON 1ST TO 28TH FLOOR.
– MECHANICAL & ELECTRICAL : WORKING PROCESS ON 1ST TO 27TH FLOOR.
– ROAD 8 HARDSCAPE : NOW WE START PILING WORK.& RC-STRUCTURE WORK